Control Panel Testing, FAT & SAT

Every WETS AI control panel goes through 13 checks in our Houston shop before it ships: build inspection, electrical tests and full functional tests with the final program. You can witness the factory acceptance test (FAT) on request, and we verify the system again on site at the site acceptance test (SAT).

What We Check on Every Panel

The same checks, in the same order, on every panel we build.

Build and inspection

  • Build matches the drawings and parts list
  • Terminal torque checked and marked
  • Wire size, color, marking and ferrules; routing and spacing
  • Ground and bond connections
  • SCCR label, nameplate, warning labels and marked field-wiring terminals

Electrical tests

  • Point-to-point wiring check
  • Ground continuity check
  • Insulation resistance on power circuits, with electronics isolated
  • Power-up: incoming voltage, phase rotation, control transformer and 24 VDC outputs

Functional tests

  • Every I/O point simulated and verified
  • PLC and HMI loaded with the final program; alarms, interlocks and sequence tested
  • Communications verified
  • VFD and overload settings recorded

Where Each Test Happens

Testing starts long before the panel ships. Each stage catches a different kind of problem, so nothing is left for startup day.

  • Build inspection checks the panel against the drawings
  • Electrical tests prove wiring, insulation and power-up
  • Functional tests run the program with simulated I/O
  • FAT in our shop, witnessed on request, then SAT on your site
Testing timeline: build inspection, electrical tests and functional tests in the WETS AI shop, the factory acceptance test which customers can witness, shipping and installation, then the site acceptance test with real field devices.
Schneider TeSys contactors with current transformers and neatly routed control wiring
Contactors and control wiring ready for testing

FAT: Proving the Panel Before It Ships

The factory acceptance test proves that the panel and its program do what the control narrative says, before the panel leaves our shop. Problems found here take minutes to fix. The same problem found on site can cost days.

You are welcome to witness the FAT at our Houston shop on request. We agree the test procedure with you in advance, work through it together, and record the results. Anything that needs fixing is corrected and retested before the panel ships.

SAT: Proving the System On Site

After installation, the site acceptance test checks the system with the real field wiring, instruments and equipment. Signals are confirmed from the field device to the HMI, and sequences are run with the actual process.

Because the panel was proven at FAT, SAT can focus on what changes on site: field connections, instrument ranges and how the process really behaves.

Water treatment filters at a customer site during commissioning, with test equipment on site
Commissioning at a customer water treatment site

How FAT and SAT Differ

FAT and SAT are two halves of the same proof.

One happens in our shop before shipping. The other happens once the panel meets your real process.

FATSAT
WhereOur Houston shopYour site, after installation
What it provesThe panel and program match the designThe system works with your process
SignalsSimulated I/OReal field devices
Who attendsOur team, and you on requestOur team and your site team
FixesMade and retested before shippingMade on site and recorded

Testing Questions

Can we witness the FAT?

Yes, on request. We agree the procedure with you in advance and work through it together at our Houston shop.

Is every panel tested, or only some?

Every panel. All 13 checks are carried out on every panel we build, whether or not a formal FAT is requested.

Is the insulation resistance test safe for the electronics?

Yes. The test is done on power circuits with drives, PLCs and other electronics isolated, so they are not exposed to the test voltage.

What happens if something fails during FAT?

It is fixed and retested before the panel ships, and the result is recorded.

Do you support the site acceptance test?

Yes. We verify the system on site at SAT with your team, using the real field devices and process.

Related Panels & Services

UL 508A Control Panels

What the UL 508A label covers, how SCCR is set, and what we check before a panel is labeled.

PLC & HMI Programming

Programs written in-house for Allen-Bradley, Siemens and Schneider Electric, tested at FAT.